Rooms / Industrial Machinery / Weld seam inspection pilot

Weld seam inspection pilot

Stopped after four monthsIndustrial MachineryComputer visionStoppedRecorded January 2026
TI
Tomas Iversen
Manufacturing engineering / Ran the pilot and made the call to stop
Status
Stopped
Month four
Spent
$95K
Before stopping
Blocker
Machine data
2 of 3 machines
Reusable later
Yes
After controls upgrade
Team
3 people
Part time
Duration
4 months
Should have been 2
Awaiting video01:24
CLIP 01 OF 6
What we set out to do
Tomas Iversen, Manufacturing engineering
Problem
Key data from this clip
GOAL
Detect weld seam porosity inline
Stated by owner
EXPECTED BENEFIT
$400K per year
Stated by owner

Everything asked, on camera

6 answers

What this was

The team wanted inline detection of weld seam porosity to avoid pulling parts for x-ray. It stopped at four months because two of three machines could not deliver usable data and no one owned fixing that. The room exists so the next team does not repeat it.

Trigger
X-ray sampling was slow and caught defects late
Why it stopped
Machine connectivity, not model performance
Restart condition
Controls upgrade planned for 2027
Transferable
The kill-criteria lesson applies to every pilot